Street and Sidewalk Projects
City Projects
- Woodville Road – Phase 1
- Old Hearne Road Widening – Phase 1
- Old Hearne Road Extension (Indian Trail to SH6)
- Old Hearne Road Reconstruction – Phase 3
- Old Reliance Road Widening
- South College Avenue Reconstruction – Phase 1
- Sulphur Springs Road & Utilities Improvements
- Mumford Road Widening – Phase 1
- Commerce Street Reconstruction – Phase 1
- Leonard-Groesbeck Road Widening
- Groesbeck Street Extension
- Hardy Weedon Traffic Signal & Road Improvements
- W. Villa Maria Shared Use Path & Lighting
City and TxDOT Partnership Projects
City Projects
Woodville Road Reconstruction Phase 1
City Job No. 332-DE-2302
Phase One of the Woodville Road Reconstruction will convert the street from an open ditch roadway to curb and
gutter and storm sewer along with replacing other utilities from North Texas Avenue to Old Hearne Road.
Woodville Road Project Area Map
General Information
- Project Manager/City Contact: Brianna Groves, P.E., C.F.M.
- Alternate City Contact: Paul Kaspar, P.E., C.F.M.
Design
- Funding Source: Solid Waste Enterprise Fund to be reimbursed by 2024 Bond Fund
- Design Engineer: RME Consulting Engineers
- Contract Amount: $296,000
- Status: In design. ROW and Easement exhibits have been completed and land acquisition offers are being made. Once land acquisition is complete, the 75% plan set will be completed and ready for City staff review.
- Updated: 11/7/24
Construction
- Funding Source: General Fund
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
Old Hearne Road Widening – Phase 1 (Wilhelm Drive to Texas Avenue)
City Job No. 332-DE-1506
Project includes the surveying and engineering design for the widening and reconstruction of Old Hearne Road from Wilhelm Drive to Texas Avenue and a short section of Sims Ave from Texas Avenue to the railroad tracks. The roadway design will convert the existing open ditch sections within the project limits to curb and gutter pavement with sidewalks for increased pedestrian safety. Utility improvements consist of 4300 feet of sanitary sewer line replacements and 5500 feet of waterline replacements. Additionally, there will be a new traffic signal installed at the intersection of Old Hearne Rd and Texas Avenue with ADA facilities, enhanced pedestrian features, and crosswalk striping.
Old Hearne Road Project Map in PDF Format
General Information
- Project Manager/City Contact: Sam Vernon, P.E., C.F.M.
- Alternate City Contact: Paul Kaspar, P.E., C.F.M.
Design
- Funding Source: General Fund
- Design Engineer: Quiddity (formally Jones & Carter)
- Contract Amount: $765,000.00
- Status: Complete
Construction
- Funding Source: General Fund
- Contractor: Larry Young Paving, Inc.
- Contract Amount: $7,618,127.00
- City Inspector: Kurk Fowler
- Status: Old Hearne Rd from Texas Ave to Wilhelm Dr is substantially complete. The contractor has some repair/clean-up remaining as well as mounting the signage. An 8″ waterline underneath the railroad tracks will be replaced with a 12″ line. This requires a permit from the railroad. Construction of the roadway from Texas Ave to the railroad tracks cannot commence until this line is in place. UPRR has had the permit under various stages of review for about 10 months. The anticipated date for the bore under the tracks is September of 2024. We anticipate another 90 days of construction once the bore has been completed.
- Updated: 11/11/24
Old Hearne Road Extension (Indian Trail to SH6)
City Job No. 332-DE-2201
The Old Hearne Road Extension project will construct approximately 1800 LF of roadway between Indian Trail and Earl Rudder Freeway, and approximately 500 LF of BRAC roadway from Old Hearne Road into the park and connecting to the future BTU administrative building site.
General Information
- Project Manager/City Contact: Eric Blackburn, E.I.T.
Design
- Funding Source: Fund 374 – 2020 Bonds
- Design Engineer: Gessner Engineering LLP
- Contract Amount: $152,500
- Status: Project should be going out to bid around November 12th with the hope that construction will start by early 2025.
- Update: 11/11/24
Construction
- Funding Source: TBD
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
Old Hearne Road Reconstruction – Phase 3 (Woodville Road to Wilkes Street)
City Job No. 332-DE-2301
The Old Hearne Road Reconstruction Ph. 3 will convert the existing street from an open ditch roadway to curb and gutter and storm sewer along with replacing other utilities from Woodville Road to Wilkes Street. This section will be a continuation of the 38-foot-wide reinforced concrete roadway with 8-feet wide sidewalks. Design will include a roundabout at the Old Hearne Road and Stevens Street intersection. Additionally, existing water lines will be upgraded and sanitary sewer lines will be constructed and upgraded.
General Information
- Project Manager/City Contact: Sarah Green, E.I.T., C.F.M.
Design
- Funding Source: 2024 Bonds
- Design Engineer: RME Consulting Engineers
- Contract Amount: $403,000.00
- Status: City is reviewing the 50% plan set submitted on 10/28/24 by the design engineer.
- Updated: 11/7/24
Construction
- Funding Source:
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
Old Reliance Road Widening
City Job No. 332-D3-1512
This contract includes providing design (including survey, environmental and geotechnical investigation, as needed), bidding, and construction phase services associated with the widening of Old Reliance Road. The general configuration includes a four-lane divided road from Austin’s Colony Parkway east to the city limits, approximately 3,650 linear feet of roadway. The project will also include 10-foot shared use path on one side of the road to provide bicycle and pedestrian access to Rudder High School.
General Information
- Project Manager/City Contact: Eric Blackburn, E.I.T.
- Alternate City Contact: Paul Kaspar, P.E., C.F.M
Design
- Funding Source: 2024 Bonds
- Design Engineer: Goodwin-Lasiter-Strong
- Contract Amount: $648,300.00
- Status: The scope of the project has expanded. Design is delayed slightly.
- Update: 11/11/24
Construction
- Funding Source:
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
Commerce Street Reconstruction – Phase 1
City Job No. 332-DE-1620
The Commerce Street Reconstruction Ph 1 project will upgrade the roadway, sidewalks, and drainage systems from Beck Street to Lee Avenue. The project will transform the current asphalt road with open ditches into a 37-foot wide concrete street with 6-foot wide sidewalks on both sides, improving safety for pedestrians and vehicles. Key infrastructure improvements include replacing existing water and sewer lines and constructing a new storm sewer system with box culverts to enhance drainage and reduce flooding. The project also involves coordinating with overhead utility relocations and preparing for street lighting by BTU. Construction began in January 2024 and is expected to be completed by the end of the year.
General Information
- Project Manager/City Contact: James Hayes, E.I.T.
- Alternate City Contact: Paul Kaspar, P.E., C.F.M.
Design
- Funding Source: Transportation Fund
- Design Engineer: RME Consulting Engineers
- Contract Amount: $91,400
- Status: Complete
Construction
- Funding Source: Transportation Fund
- Contractor: Norman Construction Services LLC
- Contract Amount: $2,957,540.00
- City Inspector: Kurk Fowler
- Status: Significant progress has been made in the month of October. Currently the contractor has completed 70% of the new concrete pavement, with the remaining concrete roadway scheduled to be poured this month. Other work left until completion include sidewalk construction, roadway striping, signage installation, and site restoration. Upon speaking with the contractor, city staff expect to the see the project near substantial completion before the end of the year.
- Updated: 11/11/24
South College Avenue Reconstruction- Phase 1
City Job No. 332-DE-2016
The project involves the reconstruction of approximately 4,300 linear feet of South College Avenue from West Villa Maria Road to Carson Street. It includes replacing and upgrading aging water and sewer facilities, including offsite sanitary sewer lines serving neighboring residential areas, and installing an underground storm sewer system. The project also includes street lighting and pedestrian improvements, with a 12-foot wide shared use path along the west side of South College Avenue and a 6-foot wide sidewalk along the east side. Replacing the aging water and sewer lines will modernize the infrastructure, while the upgraded storm sewer network will enhance the stormwater drainage system to reduce localized flooding. This project will improve the safety and efficiency of the roadway for both vehicular and pedestrian traffic and aims to encourage neighborhood revitalization and promote economic development in the area.
Monthly Update Letters
South College Avenue Project Map in PDF Format
Please Submit Questions/Comments
**NEW** Interactive Story Map
General Information
- Project Manager/City Contact: James Hayes, E.I.T.
- Alternate City Contact: Paul Kaspar, P.E., C.F.M.
Design
- Funding Source: General Fund
- Design Engineer: Goodwin Lasiter Strong
- Contract Amount: $547,455.00
- Status: Complete
Construction
- Funding Source: General Fund, Water Fund, & Sanitary Sewer Fund
- Contractor: Larry Young Paving, Inc
- Contract Amount: $15,990,929.00
- City Inspector: Alan Mitchell/Max Dimas
- Status: In the past month, LYP has opened the section of South College Ave from Villa Maria to Dellwood. Their next goal is to open up to Edge St.
Currently, LYP is also working between Bizzell St. and Williamson Dr./Hollydale St. They have scheduled 450 cubic yards of concrete to be poured for the southbound lane from STA 20+00 to 28+50 on 11/14/24. If this pour is successful, the northbound lane is expected to be completed the following week, with the aim of completing this entire section before Thanksgiving.
Engineering staff are actively collaborating with LYP to keep the project on schedule. In the past two weeks, the city has met with LYP to assess the feasibility and potential impacts of expediting the main roadway opening on South College Ave. The City has requested an early opening to allow public access to portions of the road before the sidewalks, shared-use path, and side streets are completed. - Updated: 11/11/2024
Detour Route – South College Reconstruction Phase 1 effective May 22nd 2023 – November 2023
Sulphur Springs Road & Utilities Improvements
City Job No. 411-611-DE-1803
This contract will provide roadway, sidewalk, water, and sewer improvements between Sulphur Springs Road and East Villa Maria Road, East of South College Avenue to Cavitt Avenue. The roadway improvements will include wider curb and gutter streets with sidewalks along one side of the street. Many of the existing public water and sewer lines in this area are substandard and located on private property. The majority of those lines will be abandoned or removed and new water and sewer lines will be placed in the Right-of-Way.
General Information
- Project Manager/City Contact: Eric Blackburn, E.I.T.
Design
- Funding Source: Fund 510 – Water & Fund 515 – Wastewater
- Design Engineer: Goodwin-Lasiter-Strong
- Contract Amount: $122,900.00
- Status: Complete
Construction
- Funding Source: Fund 240 – Transportation, Fund 510 – Water, & Fund 515 – Wastewater
- Contractor: Norman Construction Services LLC
- Contract Amount: $3,214,208.00
- City Inspector: Alan Mitchell/Max Dimas
- Status: Total construction is approximately 81% complete. All utility installations are complete. Roadway improvements continue.
- Update: 11/11/24
Mumford Rd Widening – Phase 1
City Job No. 332-D3-2329
This contract will reconstruct and widen the roadway to a width of 38′ with a continuous center turn lane. Approximately 6400 linear feet of road beginning at the intersection of Mumford Rd and FM 2818 (Harvey Mitchell Pkwy) to approximately 460 linear feet from Carrier Ln. In addition to road widening, drainage improvements will include curb inlets, storm sewer and a 26-foot wide by approximately 60-foot span bridge. Street lighting is also proposed.
General Information
- Project Manager/City Contact: Eric Blackburn, E.I.T.
Design
- Funding Source: 2024 Bonds
- Design Engineer: Goodwin-Lasiter-Strong
- Contract Amount: $596,200.00
- Status: 90% plan set submittal expected soon.
- Update: 11/11/24
Construction
- Funding Source:
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
Leonard-Groesbeck Road Widening
City Job No. 332-411-425-611-DE-2417
With the current rate of development of Bryan’s west side, the need for roadway improvements has increased in order to continue to facilitate growth and connectivity within the City. Leonard/Groesbeck is classified as a minor arterial. The existing roadway is asphalt pavement with an open ditch drainage system. There are existing underground and pole mounted utilities within the right of way. There is an existing culvert crossing at Turkey Creek. The limits of the project are from FM 2818 (Harvey Mitchell Parkway) to the recently constructed roundabout at the intersection of Palasota and Groesbeck, approximately 10,500 linear feet of roadway. Groesbeck turns into Leonard Road at Bellaire Blvd.
The proposed section is currently planned as a 54-foot wide curbed concrete roadway with sidewalks on both sides. The street would be single lanes, a two-way center turn lane, and striped bicycle lanes. Sidewalks are planned on both sides of Leonard/Groesbeck. FM 1688 is currently under design through TxDOT. Leonard Road changes into FM 1688 at Harvey Mitchell Parkway, so coordination between designs may mean changes in the proposed section. Curbs, curb inlets, and storm sewer pipes will replace the open ditch drainage.
General Information
- Project Manager/City Contact: Sarah Green, E.I.T., C.F.M.
- Alternate City Contact: Paul Kaspar, P.E., C.F.M.
Design
- Funding Source: General Fund
- Design Engineer: TBD
- Contract Amount: TBD
- Status: The City received proposals for the design contract in late Summer 2024. Contract negotiations are now in the final stages.
- Update: 11/7/24
Construction
- Funding Source:
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
Groesbeck Street Extension
City Job No. 332-D3-2330
The Groesbeck Extension project will extend a new road between S. College and Texas Avenue aligning with E 32nd Street. This project is envisioned as a key piece to regional mobility providing a connection to University Drive to the East and SH 47 to the West utilizing Groesbeck and Leonard Roads to connect to SH 47. The proposed road section is a 38-foot wide, 3 lane minor collector with center 2 way turn lane, curb and gutter with a sidewalk and shared use path and an urban storm sewer system with standard roadway lighting. The project will include a traffic signal installation at the Texas Avenue intersection.
General Information
- Project Manager/City Contact: Eric Blackburn, E.I.T.
- Alternate City Contact: Paul Kaspar, P.E., C.F.M.
Design
- Funding Source: 2024 Bonds
- Design Engineer: Bleyl Engineering
- Contract Amount: $240,070.00
- Status: Meetings with property owners regarding the acquisition of Rights-of-Way are continuing. Detailed design will start when ROW is acquired.
- Update: 11/11/24
Construction
- Funding Source:
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
Hardy Weedon Traffic Signal & Road Improvement
City Job No. 332-DE-2203
Design
- Funding Source: General Fund
- Design Engineer: Bleyl Engineering
- Contract Amount: $173,000
- Status: Awaiting submittal of revised plans from the contractor.
- Update: 11/11/24
Construction
- Funding Source:
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
W. Villa Maria Shared Use Path & Lighting
City Job No. 350-D8-2108
Design
- Funding Source: TASA Grant/2022 Bond Fund
- Design Engineer: Goodwin-Lasiter-Strong
- Contract Amount: $323,000
- Status: Complete
Construction
- Status: Phase 1 Construction is 85% complete. One of the two easements needed from two local businesses for the project is complete. Progress remains halted as property owner & the City work toward finalizing the second easement agreement. Phase 2 of the project is in negotiations. The designer has been selected and a draft of the proposal has been reviewed and comments returned. A revised design contract is expected within the month.
- Updated: 11/7/24
City and TxDOT Partnership Projects
William J. Bryan Pkwy (FM 158) Improvements
City Job No. 700-DE-1710
The City of Bryan, in partnership with the Texas Department of Transportation and the Bryan/College Station Metropolitan Planning Organization, is planning safety and mobility improvements for William J. Bryan Parkway from Texas Avenue to SH 6.
This project will include improving pedestrian, cyclist and vehicular access and safety; reducing chronic traffic congestion along the corridor; improving access to Sue Haswell Park; and improvements to utilities and drainage.
WJB Project Map in PDF Format
Click Here to Learn More About the William J. Bryan Pkwy Improvement Project
General Information
- Project Manager/City Contact: Brianna Groves, P.E., C.F.M.
- Alternate City Contact: Sam Vernon, P.E., C.F.M.
Design
- Funding Source: Transportation Fee; General Fund
- Design Engineer: Binkley & Barfield
- Contract Amount: $1,024,119.66
- Status: Design is 100% complete.
Construction
- Funding Source: TxDOT Project
- Contractor: Larry Young Paving
- Contract Amount: TxDOT Project
- Status: Construction is currently in progress.
- Updated: 11/11/24
Texas Avenue Infrastructure Improvements
City Job No. 332-DE-1904
Project consists of improvements to Texas Ave from Old Hearne Road to University Drive.
General Information
- Project Manager/City Contact: Zach Kennard, P.E.
- Alternate City Contact: Paul Kaspar, P.E., C.F.M.
Design
- Funding Source: General Fund, Transportation Fund
- Design Engineer: Lockwood, Andrews & Newman, Inc.
- Contract Amount: $2,231,146.16
- Status: All phases are complete.
Construction
- Funding Source: TxDOT/MPO
- Contractor: – Larry Young Paving, Inc.
- Contract Amount: TxDOT project
- City Inspector: TxDOT project
- Status: In progress. Additional phases to begin in 2026.
- Updated: 11/11/24