Skip to main content

City of Bryan, Texas

MORE
INFO  ›

x

facebook icon twitter icon instagram icon flickr icon youtube icon NextDoor icon

Drainage Projects

Drainage Projects

Flood Studies

Drainage Projects

Bristol St & Esther Blvd Drainage Improvements

City Job No. 425-D2-1910

This contract will include, replacement of existing storm sewer collection system to increase capacity to Burton Creek,  new storm sewers to be installed within existing right-of-ways. Reconstruction of concrete streets where new storm sewer will be installed, resizing and addition of storm inlets to increase capture capacity, and 2D modeling.

Bristol & Esther Project Map in PDF Format

General Information

Design

  • Funding Source: Fund 245 – Drainage Fee
  • Design Engineer: Walker Partners LLC
  • Contract Amount: $354,500.00
  • Status: Complete

Construction

  • Funding Source: Fund 245 – Drainage Fee
  • Contractor: Texcon General Contractors
  • Contract Amount: $ 7,264,127.39
  • City Inspector: Max Dimas
  • Status: Construction is 6% complete. Work continues on Esther Blvd to install the main drainage culverts for this project. These culverts are 4 foot tall and 10 foot wide, greatly increasing the amount of water that can be drained from the area.
  • Updated: 2/11/25

 

Briar & Burton Creek Slope Stabilization Project

City Job No. 425-D2-2102

This contract will address the stability of Briar & Burton Creek banks occurring along the unlined segment of the channel. In 2020, construction of the concrete lining of part of the channel was completed. The scope of this project is stabilization from the existing concrete lining to the end of the channel at N. Earl Rudder Freeway Western Frontage Road, approximately 900-feet of Briar Creek.

General Information

  • Project Manager/City Contact: James Hayes, E.I.T.

Design

  • Funding Source: Capital Reserve Fund
  • Design Engineer: Freese & Nichols
  • Contract Amount: $306,933.00
  • Status: This project will continue stabilizing Burton Creek from the golf course to highway 6. The project is dependent on the TxDOT Highway 6 expansion project and is expected to enter construction after the TxDOT crews have completed work in the area.

Construction

  • Funding Source:
  • Contractor: TBD
  • Contract Amount:  TBD
  • City Inspector: TBD
  • Status:
  • Updated: 2/11/25

 

Hillside Oaks & Old Oaks Drainage Improvements

City Job No. 332-425-DE-2026

The contract is a neighborhood drainage improvements project aimed to alleviate lot flooding and improve surface drainage throughout The Oaks neighborhood. The scope consists of
installation of new, and upsizing of existing, storm sewer. Additionally, the local streets will be re-constructed following storm sewer installation, with the inversion of Hillside Drive and installation of a trench drain down the center of the inverted street.

General Information

  • Project Manager/City Contact: Sarah Green, E.I.T.
  • Alternate City Contact: Paul Kaspar, P.E., C.F.M.

Design

  • Funding Source: Fund 245 – Drainage Fee
  • Design Engineer: Goodwin Lasiter Strong
  • Contract Amount:$236,500
  • Status: Complete

Construction

  • Funding Source: Fund 245 – Drainage Fee
  • Contractor: Texcon General Contractors
  • Contract Amount: $3,049,293.00
  • City Inspector: Michael Oliver
  • Status: Construction is approximately 96% complete.
  • Updated: 2/11/25

 

Wayside Drive Storm Sewer Improvements

City Job No. 425-D1-2028 

This project includes the analysis of and improvements to storm water infrastructure in various locations along Wayside Drive.

General Information

  • Project Manager/City Contact: Jon MacKay, E.I.T.

Design

  • Funding Source: General Fund
  • Design Engineer: Gessner Engineering
  • Contract Amount: $110,000
  • Status: Staff held a meeting with the designer & had a site visit to clear up any questions before preparing the final plans for the project. The designing engineer is updating the plans to include items and ideas found out during the site visit.

Feedback Form: Share Your Thoughts

Construction

  • Funding Source:  General Fund
  • Contractor: TBD
  • Contract Amount:  TBD
  • City Inspector: TBD
  • Status: 2/11/25

 

Briar Creek Floodplain Modeling

City Job No. 425-D1-0004

Through this contract, the Consultant will update the rainfall and runoff generation (hydrologic) and floodplain (hydraulic) modeling for Briar Creek, using updated topographic information as well as more accurate information related to the Carter’s Creek floodplain which significantly affects this watershed. The results of the updated models will be provided to FEMA for the Letter of Map Revision (LOMR) process to update the community Flood Insurance Rate Maps.

Briar Creek Project Map in PDF Format

General Information

  • Project Manager/City Contact: Paul Kaspar, P.E., C.F.M.

Design

    • Funding Source: Fund 245 – Drainage Fee
    • Design Engineer: Mitchell & Morgan
    • Contract Amount: $32,200.00
    • Status: FEMA Submittal
    • Updated: 2/11/25