Skip to main content

City of Bryan, Texas

MORE
INFO  ›

x

facebook icon twitter icon instagram icon flickr icon youtube icon NextDoor icon

General Projects

Bryan Midtown Park Improvements

City Job No. 700-D0-1712/572-D1-1811

This project is to provide improvements to the park.

Bryan Midtown Park Project Map in PDF Format

General Information

  • Project Manager/City Contact: Frank Clark
  • Alternate City Contact: Paul Kaspar, P.E., C.F.M.

Design

  • Funding Source: Capital Reserve Fund
  • Design Engineer: Mitchell & Morgan
  • Contract Amount: $2,622,79.05

Construction 

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2002
  • Contractor: Palasota Contracting LLC
  • Contract Amount: $2,756,991.50
  • City Inspector: Mike Nobles
  • Status: Phase 1B & 3A – Bomber Drive & Deceleration Lane are complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2013
  • Contractor: Construction Rent-A-Fence
  • Contract Amount: $37,166.25
  • City Inspector: Alan Mitchell
  • Status: Phase 1C – Travis Field is complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2003
  • Contractor: Marek Bros Construction, Inc.
  • Contract Amount: $544,000.40
  • City Inspector: Mike Nobles
  • Status: Phase 1D – Gateway Landscaping is complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2010
  • Contractor: Palasota Contracting LLC
  • Contract Amount: $1,148,190.95
  • City Inspector: Alan Mitchell
  • Status: Phase 2 – Big Shots Access Driveway is complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2011
  • Contractor: Kelly Burt Dozer
  • Contract Amount: $719,901.58
  • City Inspector: Mike Nobles
  • Status: Big Shots Detention Pond is complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2010
  • Contractor: Solitude Lake Management
  • Contract Amount: $45,000
  • City Inspector: Mike Nobles
  • Status: Phase 3B – Fish Relocation is complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2017
  • Contractor: Palasota Contracting LLC
  • Contract Amount: $3,667,960.00
  • City Inspector: Alan Mitchell
  • Status: Phase 3C – Lake Earthwork is complete. This will stay until total project is complete.

Design

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2219
  • Contractor: Walker Partners
  • Contract Amount: $123,850.00
  • City Inspector: Alan Mitchell
  • Status:  Phase 3C-2 – Boardwalk – Construction is scheduled to start 2/17/2025.
  • Updated: 2/10/2025

Construction

  • Funding Source: Fund 377 – 2026 Bonds
  • City Job No. 700 -D0-2219
  • Contractor: Bartlett Cocke General Contractors
  • Contract Amount: $4,198,152.34
  • City Inspector: Alan Mitchell
  • Status:  Phase 3C-2 – Boardwalk – Construction is scheduled to start 2/17/2025.
  • Updated: 2/10/2025

Design

  • Funding Source: TBD
  • City Job No. 700 -D0-2117
  • Contractor: TBD
  • Contract Amount: TBD
  • City Inspector: Alan Mitchell
  • Status:  Phase 3C-3 – Dam & Spillway – The TCEQ Water Rights permit has been approved/granted.
  • Updated: 2/10/2025

Construction

  • Funding Source: Fund 377 – 2026 Bonds
  • City Job No. 700 -D0-2209
  • Contractor: Brien Water Wells
  • Contract Amount: $1,537,139.85
  • City Inspector: Alan Mitchell
  • Status: Phase 3C-4 – Water Wells – City Council approved at the January 2025 session. Brien Water Wells will begin construction in late February 2025.
  • Updated: 2/11/2025

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2024
  • Contractor: Palasota Contracting LLC
  • Contract Amount: $2,053,110.20
  • City Inspector: Alan Mitchell
  • Status: Phase 3D – Outer Loop Trail – Construction is substantially complete.
  • Updated: 2/11/2025

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2011
  • Contractor: Norman Construction Services, LLC.
  • Contract Amount: $1,039,439.00
  • City Inspector: Alan Mitchell
  • Status: Phase 3E – Carson St Detention Pond is complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2029
  • Contractor: Larry Young Paving, LLC.
  • Contract Amount: $4,996,227.06
  • City Inspector: Alan Mitchell
  • Status: Phase 5A -Midtown Blvd is complete. This will stay until total project is complete.

Design/Construction

  • Funding Source: General Fund
  • City Job No. 700 -D0-2323
  • Contractor: SpawGlass
  • Contract Amount: $4,500,000.00
  • City Inspector: Alan Mitchell
  • Status: Phase 5D – Playground – In Design. Staff await approval of conceptual design/cost.
  • Updated: 2/11/2025

Construction

  • Funding Source: General Fund
  • City Job No. 700-D0-2208
  • Contractor: Brazos Paving Inc.
  • Contract Amount: $7,853,697.77
  • City Inspector: Alan Mitchell
  • Status: Phase 8A- Road A – The project is in the punchlist phase. City staff are optimistic that final acceptance of the project may be achieved early 2025.
  • Updated: 2/11/2025

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2210
  • Contractor: Caffey & Sons, Inc.
  • Contract Amount: $488,640.00
  • City Inspector: Alan Mitchell
  • Status: Phase 9C – Marquee Signage is complete. This will stay until total project is complete.

 

Railroad Quiet Zones Streetscaping

City Job No. 332-D3-1108

This project is to provide safety and acoustical improvements along the railroad corridor in Bryan.

General Information

  • Project Manager/City Contact: Sarah Green, E.I.T., C.F.M.
  • Alternate City Contact: Paul Kaspar, P.E., C.F.M.

Design

  • Funding Source: Transportation Fund
  • Design Engineer: CTC, Inc.
  • Contract Amount: $22,698.00
  • Status: Complete

Construction

  • Funding Source: General Fund Bonds
  • CIP Budget: $5,517,000.00
  • Contractor: Brazos Paving, Inc.
  • Contract Amount: $657,991.00
  • City Inspector: Kurk Fowler
  • Status: Contractor is working on final punchlist items. Rain is needed to ensure the culvert at MLK is providing ample drainage. The project will remain open until the culvert can be tested.
  • Updated: 1/7/2025

 

Briarcrest Dr Traffic Signals

This project will improve traffic signals at Briarcrest Dr at Broadmoor Dr and Briarcrest Dr at Villa Maria Rd.

City Job No. 750-D7-1816

General Information

  • Project Manager/City Contact: Zachary Kennard, P.E.

Design

  • Funding Source: Fund 240 – Street Fund
  • Design Engineer: Binkley & Barfield
  • Contract Amount: $59,600.00
  • Status: Complete

Construction

  • Funding Source: Fund 240 – Street Fund
  • City Job No. 750-D7-1816
  • Contractor: Bayer Construction
  • Contract Amount: $1,012,726.48
  • City Inspector: Alan Mitchell
  • Status: New traffic signals in operation 2nd week of February. Flatwork to be performed in the coming weeks.
  • Updated: 2/10/2025

 

E 29th St Traffic Signals Phase 2

City Job No. 750-D7-2403

This project will improve traffic signals at East 29th Street at Still Meadow Drive and East 29th Street at Barak Lane.

General Information

  • Project Manager/City Contact: Zachary Kennard, P.E.

Design

  • Funding Source: Fund 240 – Street Fund
  • Design Engineer: Kimley Horn & Associates
  • Contract Amount: $124,235.00
  • Status: Notice to Proceed sent to the design firm; staff awaiting first submittal. Contract amount is for contractor services relating to 2 projects – 29th St Traffic Signals Ph 2 and South College at North Ave Traffic Signal.

Construction

  • Funding Source: Fund 240 – Street Fund
  • Contractor: TBD
  • Contract Amount: TBD
  • City Inspector: TBD
  • Status:
  • Updated: 2/10/2025

 

2024 Major Corridor Signal Timing

City Job No. 750-D7-2413

General Information

  • Project Manager/City Contact: Zachary Kennard, P.E.

Design

  • Funding Source: Fund 240 – Street Fund
  • Design Engineer:
  • Contract Amount:
  • Status: Paused negotiation. Traffic Operations Supervisor would like to install new Advanced Traffic Signal Performance Measures (ATSPM) technology prior to performing any retiming.

Construction

  • Funding Source: Fund 240 – Street Fund
  • Contractor: TBD
  • Contract Amount: TBD
  • City Inspector: TBD
  • Status:2/10/2025

 

South College and North Ave Traffic Signal

City Job No. 750-D7-2409

This project will improve traffic signal located at the intersection of North Avenue and South College Avenue.

General Information

  • Project Manager/City Contact: Zachary Kennard, P.E.

Design

  • Funding Source: Fund 240 – Street Fund
  • Design Engineer: Kimley Horn & Associates
  • Contract Amount: $124,235.00
  • Status: Notice to Proceed sent to the design firm; staff awaiting first submittal. Contract amount is for contractor services relating to 2 projects: 29th St Traffic Signals Ph 2 and South College at North Ave Traffic Signal.

Construction

  • Funding Source: Fund 240 – Street Fund
  • Contractor: TBD
  • Contract Amount: TBD
  • City Inspector: TBD
  • Status:
  • Updated: 2/10/2025