General Projects

Bryan Midtown Park Improvements

City Job No. 700-D0-1712/572-D1-1811

This project is to provide improvements to the park.

Bryan Midtown Park Project Map in PDF Format

General Information

  • Project Manager/City Contact: Frank Clark
  • Alternate City Contact: Paul Kaspar, P.E., C.F.M.

Design

  • Funding Source: Capital Reserve Fund
  • Design Engineer: Mitchell & Morgan
  • Contract Amount: $2,622,79.05

Construction 

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2002
  • Contractor: Palasota Contracting LLC
  • Contract Amount: $2,756,991.50
  • City Inspector: Mike Nobles
  • Status: Phase 1B & 3A – Bomber Drive & Deceleration Lane are complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2013
  • Contractor: Construction Rent-A-Fence
  • Contract Amount: $37,166.25
  • City Inspector: Alan Mitchell
  • Status: Phase 1C – Travis Field is complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2003
  • Contractor: Marek Bros Construction, Inc.
  • Contract Amount: $544,000.40
  • City Inspector: Mike Nobles
  • Status: Phase 1D – Gateway Landscaping is complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2010
  • Contractor: Palasota Contracting LLC
  • Contract Amount: $1,148,190.95
  • City Inspector: Alan Mitchell
  • Status: Phase 2 – Big Shots Access Driveway is complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2011
  • Contractor: Kelly Burt Dozer
  • Contract Amount: $719,901.58
  • City Inspector: Mike Nobles
  • Status: Big Shots Detention Pond is complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2010
  • Contractor: Solitude Lake Management
  • Contract Amount: $45,000
  • City Inspector: Mike Nobles
  • Status: Phase 3B – Fish Relocation is complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2017
  • Contractor: Palasota Contracting LLC
  • Contract Amount: $3,667,960.00
  • City Inspector: Alan Mitchell
  • Status: Phase 3C – Lake Earthwork is complete. This will stay until total project is complete.

Design

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2219
  • Contractor: Walker Partners
  • Contract Amount: $123,850.00
  • City Inspector: Alan Mitchell
  • Status:  Phase 3C-2 – Boardwalk – Construction is scheduled to start 3/10/2025.
  • Updated: 3/12/2025

Construction

  • Funding Source: Fund 377 – 2026 Bonds
  • City Job No. 700 -D0-2219
  • Contractor: Bartlett Cocke General Contractors
  • Contract Amount: $4,198,152.34
  • City Inspector: Alan Mitchell
  • Status:  Phase 3C-2 – Boardwalk – Construction is scheduled to start 3/10/2025.
  • Updated: 3/12/2025

Design

  • Funding Source: TBD
  • City Job No. 700 -D0-2117
  • Contractor: TBD
  • Contract Amount: TBD
  • City Inspector: Alan Mitchell
  • Status:  Phase 3C-3 – Dam & Spillway – The TCEQ Water Rights permit has been approved/granted. Expected to post request for bids in Mid-March.
  • Updated: 3/12/2025

Construction

  • Funding Source: Fund 377 – 2026 Bonds
  • City Job No. 700 -D0-2209
  • Contractor: Brien Water Wells
  • Contract Amount: $1,537,139.85
  • City Inspector: Alan Mitchell
  • Status: Phase 3C-4 – Water Wells – Contractor was issued the Notice to Proceed. Construction activity should start late spring. Contract end date is in December 2025.
  • Updated: 3/12/2025

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2024
  • Contractor: Palasota Contracting LLC
  • Contract Amount: $2,053,110.20
  • City Inspector: Alan Mitchell
  • Status: Phase 3D – Outer Loop Trail – Construction is substantially complete.
  • Updated: 2/11/2025

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2011
  • Contractor: Norman Construction Services, LLC.
  • Contract Amount: $1,039,439.00
  • City Inspector: Alan Mitchell
  • Status: Phase 3E – Carson St Detention Pond is complete. This will stay until total project is complete.

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2029
  • Contractor: Larry Young Paving, LLC.
  • Contract Amount: $4,996,227.06
  • City Inspector: Alan Mitchell
  • Status: Phase 5A -Midtown Blvd is complete. This will stay until total project is complete.

Design/Construction

  • Funding Source: General Fund
  • City Job No. 700 -D0-2323
  • Contractor: SpawGlass
  • Contract Amount: $4,500,000.00
  • City Inspector: Alan Mitchell
  • Status: Phase 5D – Playground – In Design. Staff await approval of conceptual design/cost.
  • Updated: 3/12/2025

Construction

  • Funding Source: General Fund
  • City Job No. 700-D0-2208
  • Contractor: Brazos Paving Inc.
  • Contract Amount: $7,853,697.77
  • City Inspector: Alan Mitchell
  • Status: Phase 8A- Road A – Project is anticipated to be complete by end of March 2025.
  • Updated: 3/12/2025

Construction

  • Funding Source: Fund 374 – 2020 Bonds
  • City Job No. 700-D0-2210
  • Contractor: Caffey & Sons, Inc.
  • Contract Amount: $488,640.00
  • City Inspector: Alan Mitchell
  • Status: Phase 9C – Marquee Signage is complete. This will stay until total project is complete.

 

Railroad Quiet Zones Streetscaping

City Job No. 332-D3-1108

This project is to provide safety and acoustical improvements along the railroad corridor in Bryan.

General Information

  • Project Manager/City Contact: Sarah Green, E.I.T., C.F.M.
  • Alternate City Contact: Paul Kaspar, P.E., C.F.M.

Design

  • Funding Source: Transportation Fund
  • Design Engineer: CTC, Inc.
  • Contract Amount: $22,698.00
  • Status: Complete

Construction

  • Funding Source: General Fund Bonds
  • CIP Budget: $5,517,000.00
  • Contractor: Brazos Paving, Inc.
  • Contract Amount: $657,991.00
  • City Inspector: Kurk Fowler
  • Status: Contractor is working on final punchlist items.
  • Updated: 3/10/2025

 

Briarcrest Dr Traffic Signals

This project will improve traffic signals at Briarcrest Dr at Broadmoor Dr and Briarcrest Dr at Villa Maria Rd.

City Job No. 750-D7-1816

General Information

  • Project Manager/City Contact: Zachary Kennard, P.E.

Design

  • Funding Source: Fund 240 – Street Fund
  • Design Engineer: Binkley & Barfield
  • Contract Amount: $59,600.00
  • Status: Complete

Construction

  • Funding Source: Fund 240 – Street Fund
  • City Job No. 750-D7-1816
  • Contractor: Bayer Construction
  • Contract Amount: $1,012,726.48
  • City Inspector: Alan Mitchell
  • Status: Traffic signals are complete. Contractor working on concrete flatwork at this time.
  • Updated: 3/10/2025

 

E 29th St Traffic Signals Phase 2

City Job No. 750-D7-2403

This project will improve traffic signals at East 29th Street at Still Meadow Drive and East 29th Street at Barak Lane.

General Information

  • Project Manager/City Contact: Zachary Kennard, P.E.

Design

  • Funding Source: Fund 240 – Street Fund
  • Design Engineer: Kimley Horn & Associates
  • Contract Amount: $124,235.00
  • Status: 60% submittal sent out for review. Comments due back by end of day March 21st. Contract amount is for contractor services relating to 2 projects – 29th St Traffic Signals Ph 2 and South College at North Ave Traffic Signal.

Construction

  • Funding Source: Fund 240 – Street Fund
  • Contractor: TBD
  • Contract Amount: TBD
  • City Inspector: TBD
  • Status:
  • Updated: 3/10/2025

 

2024 Major Corridor Signal Timing

City Job No. 750-D7-2413

General Information

  • Project Manager/City Contact: Zachary Kennard, P.E.

Design

  • Funding Source: Fund 240 – Street Fund
  • Design Engineer:
  • Contract Amount:
  • Status: Paused negotiation. Traffic Operations Supervisor would like to install new Advanced Traffic Signal Performance Measures (ATSPM) technology prior to performing any retiming.

Construction

  • Funding Source: Fund 240 – Street Fund
  • Contractor: TBD
  • Contract Amount: TBD
  • City Inspector: TBD
  • Status: 3/10/2025

 

South College and North Ave Traffic Signal

City Job No. 750-D7-2409

This project will improve traffic signal located at the intersection of North Avenue and South College Avenue.

General Information

  • Project Manager/City Contact: Zachary Kennard, P.E.

Design

  • Funding Source: Fund 240 – Street Fund
  • Design Engineer: Kimley Horn & Associates
  • Contract Amount: $124,235.00
  • Status: 60% submittal sent out for review. Comments due back by end of day March 21st.  Contract amount is for contractor services relating to 2 projects: 29th St Traffic Signals Ph 2 and South College at North Ave Traffic Signal.

Construction

  • Funding Source: Fund 240 – Street Fund
  • Contractor: TBD
  • Contract Amount: TBD
  • City Inspector: TBD
  • Status:
  • Updated: 3/10/2025