General Projects
- Bryan Midtown Park Project
- Railroad Quiet Zone Streetscaping
- Gateway Monument Signing
- Traffic Signal Improvements
Bryan Midtown Park Improvements
City Job No. 700-D0-1712/572-D1-1811
This project is to provide improvements to the park.
Bryan Midtown Park Project Map in PDF Format
General Information
- Project Manager/City Contact: Frank Clark
- Alternate City Contact: Paul Kaspar, P.E., C.F.M.
Design
- Funding Source: Capital Reserve Fund
- Design Engineer: Mitchell & Morgan
- Contract Amount: $2,622,79.05
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2002
- Contractor: Palasota Contracting LLC
- Contract Amount: $2,756,991.50
- City Inspector: Mike Nobles
- Status: Phase 1B & 3A – Bomber Drive & Deceleration Lane are complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2013
- Contractor: Construction Rent-A-Fence
- Contract Amount: $37,166.25
- City Inspector: Alan Mitchell
- Status: Phase 1C – Travis Field is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2003
- Contractor: Marek Bros Construction, Inc.
- Contract Amount: $544,000.40
- City Inspector: Mike Nobles
- Status: Phase 1D – Gateway Landscaping is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2010
- Contractor: Palasota Contracting LLC
- Contract Amount: $1,148,190.95
- City Inspector: Alan Mitchell
- Status: Phase 2 – Big Shots Access Driveway is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2011
- Contractor: Kelly Burt Dozer
- Contract Amount: $719,901.58
- City Inspector: Mike Nobles
- Status: Big Shots Detention Pond is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2010
- Contractor: Solitude Lake Management
- Contract Amount: $45,000
- City Inspector: Mike Nobles
- Status: Phase 3B – Fish Relocation is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2017
- Contractor: Palasota Contracting LLC
- Contract Amount: $3,667,960.00
- City Inspector: Alan Mitchell
- Status: Phase 3C – Lake Earthwork is complete. This will stay until total project is complete.
Design
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2219
- Contractor: Walker Partners
- Contract Amount: $123,850.00
- City Inspector: Alan Mitchell
- Status: Phase 3C-2 – Boardwalk – The project is out to bid with an opening scheduled for December 11th.
- Updated: 12/9/2024
Construction
- Funding Source:
- City Job No. 700 -D0-2209
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: Alan Mitchell
- Status: Phase 3C-4 – Water Wells – The Midtown Park Water Wells project was posted on the Brazos Bid website on September 23, 2024. After no attendance at the Pre-Bid meeting on October 4, the bid opening date was extended to October 31 to allow additional time for bidding. Only one proposal was received, and City staff are currently evaluating it. A decision regarding award anticipated to be presented at the January City Council Meeting.
- Updated: 12/10/24
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2024
- Contractor: Palasota Contracting LLC
- Contract Amount: $2,053,110.20
- City Inspector: Alan Mitchell
- Status: Phase 3D – Outer Loop Trail – Construction is substantially complete.
- Updated: 12/9/2024
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2011
- Contractor: Norman Construction Services, LLC.
- Contract Amount: $1,039,439.00
- City Inspector: Alan Mitchell
- Status: Phase 3E – Carson St Detention Pond is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2029
- Contractor: Larry Young Paving, LLC.
- Contract Amount: $4,996,227.06
- City Inspector: Alan Mitchell
- Status: Phase 5A -Midtown Blvd is complete. This will stay until total project is complete.
Design/Construction
- Funding Source: General Fund
- City Job No. 700 -D0-2323
- Contractor: SpawGlass
- Contract Amount: $4,500,000.00
- City Inspector: Alan Mitchell
- Status: Phase 5D – Playground – In Design. Staff await approval of conceptual design/cost.
- Updated: 12/9/24
Construction
- Funding Source: General Fund
- City Job No. 700-D0-2208
- Contractor: Brazos Paving Inc.
- Contract Amount: $7,853,697.77
- City Inspector: Alan Mitchell
- Status: Phase 8A- Road A – The project has reached Substantial Completion. This month, we will conduct a Punchlist Inspection to identify any outstanding items that require correction. Following the inspection, a list of these items will be provided to the contractor for resolution. City staff are optimistic that final acceptance of the project may be achieved early 2025.
- Updated: 12/10/24
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2210
- Contractor: Caffey & Sons, Inc.
- Contract Amount: $488,640.00
- City Inspector: Alan Mitchell
- Status: Phase 9C – Marquee Signage is complete. This will stay until total project is complete.
Railroad Quiet Zones Streetscaping
City Job No. 332-D3-1108
This project is to provide safety and acoustical improvements along the railroad corridor in Bryan.
General Information
- Project Manager/City Contact: Sarah Green, E.I.T., C.F.M.
- Alternate City Contact: Paul Kaspar, P.E., C.F.M.
Design
- Funding Source: Transportation Fund
- Design Engineer: CTC, Inc.
- Contract Amount: $22,698.00
- Status: Complete
Construction
- Funding Source: General Fund Bonds
- CIP Budget: $5,517,000.00
- Contractor: Brazos Paving, Inc.
- Contract Amount: $657,991.00
- City Inspector: Kurk Fowler
- Status: The contractor is working to complete the final punchlist.
- Updated: 12/10/24
Gateway Monument Sign
City Job No. 700-DE-1712
This project will install two new gateway monument signs for the City of Bryan located in the following areas: along Hwy 6 between TX-OSR and Louis E Mikulin Rd, and along Hwy 21 at the northwest corner of the RELLIS campus.
General Information
- Project Manager/City Contact: Eric Blackburn, EIT
- Alternate City Contact: Paul Kaspar, P.E., C.F.M.
Design
- Funding Source: General Fund
- Design Engineer: RVI Planning & Landscape Architecture, Inc.
- Contract Amount: $23,600.00
- Status: Complete
Construction
- Funding Source: General Fund
- City Job No. 700 -DE-1712
- Contractor: Kubacak Construction, LLC
- Contract Amount: $336,620.96
- City Inspector: Michael Oliver
- Status: Project is complete
- Updated: 12/18/24
Briarcrest Dr Traffic Signals
This project will improve traffic signals at Briarcrest Dr at Broadmoor Dr and Briarcrest Dr at Villa Maria Rd.
City Job No. 750-D7-1816
General Information
- Project Manager/City Contact: Zachary Kennard, P.E.
Design
- Funding Source: Fund 240 – Street Fund
- Design Engineer: Binkley & Barfield
- Contract Amount: $59,600.00
- Status: Complete
Construction
- Funding Source: Fund 240 – Street Fund
- City Job No. 750-D7-1816
- Contractor: Bayer Construction
- Contract Amount: $1,012,726.48
- City Inspector: Alan Mitchell
- Status: Construction is approximately 45% complete.
- Updated: 12/18/24
E 29th St Traffic Signals Phase 2
City Job No. 750-D7-2403
This project will improve traffic signals at East 29th Street at Still Meadow Drive and East 29th Street at Barak Lane.
General Information
- Project Manager/City Contact: Zachary Kennard, P.E.
Design
- Funding Source: Fund 240 – Street Fund
- Design Engineer: Kimley Horn & Associates
- Contract Amount: $124,235.00
- Status: Notice to Proceed sent to the design firm; staff awaiting first submittal. Contract amount is for contractor services relating to 2 projects – 29th St Traffic Signals Ph 2 and South College at North Ave Traffic Signal.
Construction
- Funding Source: Fund 240 – Street Fund
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
- Status:
- Updated: 12/5/24
2024 Major Corridor Signal Timing
City Job No. 750-D7-2413
General Information
- Project Manager/City Contact: Zachary Kennard, P.E.
Design
- Funding Source: Fund 240 – Street Fund
- Design Engineer:
- Contract Amount:
- Status: Paused negotiation. Traffic Operations Supervisor would like to install new Advanced Traffic Signal Performance Measures (ATSPM) technology prior to performing any retiming.
Construction
- Funding Source: Fund 240 – Street Fund
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
- Status:
- Updated: 12/5/24
South College and North Ave Traffic Signal
City Job No. 750-D7-2409
This project will improve traffic signal located at the intersection of North Avenue and South College Avenue.
General Information
- Project Manager/City Contact: Zachary Kennard, P.E.
Design
- Funding Source: Fund 240 – Street Fund
- Design Engineer: Kimley Horn & Associates
- Contract Amount: $124,235.00
- Status: Notice to Proceed sent to the design firm; staff awaiting first submittal. Contract amount is for contractor services relating to 2 projects: 29th St Traffic Signals Ph 2 and South College at North Ave Traffic Signal.
Construction
- Funding Source: Fund 240 – Street Fund
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
- Status:
- Updated: 12/5/24